Baseball Field Construction Updates



1/25/2006 Construction of the baseball field is now complete. The baseball stadium is now in the permitting/design phase.
10/11/2005 Outside of the sod installation, the remainder of the field is complete, with final inspection scheduled for this coming Thursday.
8/4/2005 Work commenced last week at baseball, and is progressing quickly, with irrigation lines being installed currently. The Sparky Anderson field will be open for play for the 2006 season.
6/6/2005 Robert Allison signed the contract for our baseball field construction last week, and we will actually see the start of field construction within six weeks. Concurrently, final grading and site preparation is in progress.
3/2/2005 Work on the baseball field is expected to start in July '05, and should be complete for the 2006 baseball season.
Feedback Form