Replace Chapel Transformer
|
There is an indentified "bad leg" by 2003 infrared. Transformer failure would result
in power outage to approximately 1/4 of the campus. The existing transformer will
be demolished and a new one installed. (This project has been completed, see pictures
of the work done below.)
|
 |
 |
Construction start date: August 2004
Expected completion date: August 2004
Construction Cost: $15,000 |
Gross square footage:
Construction By:
Project Status: Completed |
|
 |
 |
Other Pictures
(Click to Enlarge)
After |
|