Library Interior Lighting Improvements
|
This project will include new under cabinet lights for 110 study carols. Existing compact
shelving will be moved to where the computer stations are near room 7, and become fixed
bookcases, the computer stations will move east in front of the old Scandinavian Cultural
Arts Center and new lighting installed above the bookshelves and computer study area. This
will greatly improve lighting and working conditions.
|
 |
 |
Construction start date: May 31, 2004
Expected completion date: August 2004
Construction Cost: $50,000 |
Gross square footage: N/A
Construction By:
Project Status: On Schedule |
|
 |
 |
Other Pictures
(Click to Enlarge)
In Progress |
|
|
|