Hutton Field


| Scope: Hutton Field opened on March 6, 2008 and is located on north campus. |
Specifics
- Architect: Sportscape International
- Construction By: Sportscape International
- Project Managers: Valerie Crooks
- Construction Start Date: Fall 2007
- Completion Date: March 2008
- Gross Square Footage: N/A
- Cost: $650,000
Status and Construction Updates
| 07/18/07 | Field design in progress; project submitted to City of Thousand Oaks for entitlement. | |||
| 11/04/07 | Field construction is well underway. Rough grading and irrigation completed; fine grading and electrical work in progress. | |||
| 01/28/08 |
|
|||
| 03/06/08 | Project Complete. Opening Ceremony on March 6, 2008 | |||