Aquatic Center Construction Updates



4/24/2006 Work is commencing on the 50-meter Samuelson Aquatics Center. Look for this project to be completed in January 2007.
1/27/2006 This project bid in December, with bids unfortunately reflecting recent escalation in steel and concrete costs. CLU Facilities is currently modifying some of the aquatics building design to cut some costs out of the project, but the project will almost certainly require additional budget funding to construct the originally planned 50 meter pool.
1/25/2006 [Currently in the permitting/design phase. Coming soon!]